The Workflow for FEED Phase

Introduction

This workflow is a good practice guidance to Engineering Managers and supporting personnel for the delivery of technical integrity. It is an ‘aide-memoir’ that highlights the key deliverables and activities throughout the lifecycle of a typical FEED project.

FEED is broken into six phases:

Phase 1: Scope Definition and Engineering Execution Strategy

Phase 2: Commencement of FEED Design

Phase 3: Initial FEED Development and Hazard Identification

Phase 4: Initial Design Review & Audit

Phase 5: FEED Design Approval (AFD)

Phase 6: Final Reviews and Feed Report Compilation

The workflow shown in the follow Road Map illustrates the execution sequence on a generic FEED Project. The vertical columns show activities that can be undertaken concurrently whilst the sequential flow of work is across the Road Map. As the deliverables and activities in each phase are completed, work can transition into the next phase.

Situations will arise when work will need to be be done out of sequence, typically to meet a demanding project schedule. Use of the workflow allows the risks of out-of-sequence working to be identified and the necessary mitigation strategies to be put in place.

HBP’s corporate governance and assurance of Engineering will measure compliance with the workflow and ensure out-of-phase working is being identified and managed. This document contains a copy of the FEED Road Map and includes detailed descriptions of the activities, the key engineering disciplines and supporting documentation.
Phase 1: Scope Definition and Engineering Execution Strategy

Preparation for commencement of detail design. To evaluate FEED deliverables to ensure engineering is sufficiently mature for detail design to progress in a controlled and minimal change environment. To confirm Engineering Execution Plan.

 Activities / DeliverablesDescriptionSupporting Documentation
1Engineering Execution Plan & Engineering Organisation ChartCreate Engineering Execution Plan complete with key supporting documents / information. 
2Preparation/Validation of Conceptual Study Report/BoDConfirm maturity of Conceptual Design report. Identify any areas of concern and ensure these are captured on the Technical Risk Register. 
3Project Baseline StandardsEstablish which codes, standards and specifications are to be utilised, e.g.. Corporate, project, client, and confirm procedure. Include in Engineering Execution Plan and/or Discipline Job Design Specifications.Engineering Baseline Standards, Document No. (DOCUMENT CODE)
4Engineering Audit ScheduleCreate formal schedule to identify when technical integrity audits, design reviews, HAZIDS, HAZOPS, etc are to be carried out. Align to Level 3 Engineering Plan and include in Engineering Execution Plan.Technical Safety Events Schedule (Lead Technical Safety Engineer)
5Technical Risk RegisterCreate formal Technical Risk Register identifying all possible risks associated with the engineering design. 
6Integrated Engineering SystemsAgree engineering design tools to be used and confirm that system hardware, software and support is available. Include issues such as PDMS or PDS, Cats and Specs, survey methods, dimensional control techniques, etc. Document and record in the Engineering Execution Plan and discipline job design specifications.Engineering Systems Project Start-up Manual, Document No. (DOCUMENT CODE)
7QRA & FRA StrategyEstablish status of project Quantitative Risk Assessment (QRA), Fire Risk Assessment (FRA) and Emergency Escape & Rescue Assessment (EERA) information and confirm methodology for timely delivery into engineering design process. Agree accountability for delivery, e.g.. Client, 3rd party, HBP, and record in Engineering Execution Plan.Hazard Management Philosophy, (DOCUMENT CODE): Hazard & Risk Management, (DOCUMENT CODE)
8Discipline Job Design SpecificationDefine the key project specific design parameters and operational constraints that are applicable to the appropriate discipline for the detailed design of the project. To identify key individuals , roles and responsibilities, design tools, key codes and standards, etc. 
9Level 3 Engineering PlanAgree work breakdown structure, develop CTRs and create level 3 integrated engineering plan covering all disciplines. To be included in Engineering Execution Plan. 
10Confirm CE Compliance StrategyReview and confirm strategy for CE Compliance. Ensure discipline Lead Engineers are aware of their responsibilities and appropriate resources / measures are in place.Corporate CE Compliance Strategy (DOCUMENT CODE); Project Compliance with Pressure Equipment Regulations (DOCUMENT CODE); Pressure Equipment Regulations Guidelines (DOCUMENT CODE); ATEX Guidelines, (DOCUMENT CODE); Machinery Directive Guidelines, (DOCUMENT CODE); Electromatic Compatibility Regulations Guidelines, (DOCUMENT CODE); MC, The Electrical Equipment (Safety) Regulations Guidelines, (DOCUMENT CODE).
11Prepare Interface RegisterDevelop interface register to ensure all interfaces are identified and managed.The Electrical Equipment (Safety) Regulations Guidelines No: (DOCUMENT CODE)

Phase 2: Commencement of FEED Design

To formally kick off the Engineering Design Process in accordance with the project execution plan and to ensure that key engineering strategies / philosophies are in place.

 Activities / DeliverablesDescriptionSupporting Documentation
1Safety Critical Systems/Elements and Performance StandardsConfirm safety critical systems / elements and set appropriate performance standards. i.e. functionality, reliability and survivability.Hazard Management Philosophy, (DOCUMENT CODE); Hazard & Risk Management, (DOCUMENT CODE); Design Verification Activities (under DCR), (DOCUMENT CODE); Platform Safety Case.
2Document Distribution MatrixCreate formal document distribution matrix to ensure all disciplines & departments receive all necessary design information in a timely manner. 
3Structural Integrity InterfaceEnsure structural integrity interfaces are identified & visible to Project, e.g. HBP / Client focal points, Technical Authorities, Independent Verification Bodies, etc. 
4Material Selection ReportReport defining the requirements and specifications of necessary material.HBP Corporate Material Engineering Specifications.
5Hazard Management PlanCreate Hazard Management Plan identifying all key hazards, technical safety activities and the approach to managing Major Accident Hazards (MAH) in the design.Hazard & Risk Management, (DOCUMENT CODE); Management of Functional Safety Guideline (DOCUMENT CODE)
6Piping SpecificationsDevelop / confirm baseline piping specifications, utilising HBP Corporate specifications where possible.HBP Corporate Piping Specifications.
7PDMS CataloguesEnsure PDMS catalogues are populated & available for all affected disciplines, utilising HBP Corporate data, i.e. CPC, where possible. 
8CMSS PhilosophyThe purpose of this task is to define and prepare the assurance activities to be undertaken aligned with the project categorisation.Develop Control Monitoring and Safety Systems (CMSS) Philosophy covering key instrumentation and control systems e.g. Process Control System (PCS), Emergency Shutdown System (ESD) and Fire and Gas (F&G).

Phase 3: Initial Design Development and Hazard Identification

To develop initial design deliverables to Inter Discipline Review (IDC) stage and identify key hazards.

 Activities / DeliverablesDescriptionKey DisciplineSupporting Documentation
1HAZIDPerform hazard identification studies, as identified on Engineering Audit Schedule / Technical Safety Events Schedule.Technical SafetyProject Hazard Identification (HAZID) (DOCUMENT CODE); Engineering & Design Reviews, (DOCUMENT CODE).
2ENVIDFormal assessment of environmental aspects associated with a modification or a change, and to propose prevention or mitigating measures.Technical SafetyEnvironmental Impact Identification (ENVID) (DOCUMENT CODE); Engineering & Design Reviews, (DOCUMENT CODE).
3PFD IDCIssue Process Flow Diagrams (PFD’s) on formal Inter-Discipline Review (IDC).Process 
4Shutdown & Blowdown PhilosophyExplains the measures to shutdown safely and control blowdown and how this will be achieved.Process 
5P&ID’s IDCIssue Piping & Instrumentation Diagrams (P&ID’s) on formal Inter-Discipline Review (IDC).Process 
6Plot Plans / Layouts IDCIssue equipment Plot Plans / Layouts on formal inter-Discipline Review (IDC).Piping and Layouts 
7HIPPS ReviewInitial review to establish requirements for a High Integrity Pressure Protection System.InstrumentsManagement of Functional Safety, (DOCUMENT CODE)
8Dropped Object StudyIdentify and assess the potential risks to drilling, production, process equipment, and manned areas from dropped or swinging objects. Where the consequence of a dropped object is considered significant, to propose prevention or mitigating measures.Technical Safety 
9Mechanical Handling StrategyDevelop Mechanical Handling Strategy including general approach / constraints, platform crane limits, installation philosophy, operation and maintenance, etc.Mechanical and Structural 
10Particular Materia Appraisals (PMA)Where required, i.e. where Corporate PMA’s or EAM’s are not suitable, develop new PMA’s and obtain approval from Notified Bodies (NoBo’s.PED Focal Point 
11C&E IDCIssue Cause & Effects for formal Inter-Discipline Review (IDC).Process and Instruments 
12Hazardous Area Layouts IDCIssue Hazardous Area Layouts for formal Inter-Discipline Review (IDC).Technical Safety 
13Fire Risk Assessment (FRA)Determines Fire & Explosion scenarios and identifies requirements for prevention, control and mitigation measures.Technical Safety 
14Blast Design PhilosophyDevelop philosophy that assesses potential explosion hazards and identifies appropriate blast loadings to be applied to the engineering design process, e.g.. Vessels, pipe supports, structural steel, etc.Technical Safety 
15TR Impairment StudyAssessment of the vulnerability of a Temporary Refuge and demonstration of its capability to sustain life for a specified duration when under attack by fire, explosion and toxic gases.Technical SafetyFire Hazards Assessment, Blast Assessment, Dispersion Assessment, Emergency, Escape and Rescue Assessment, Heat Stess Assessment
16Equipment List & Data SheetsCreate master project equipment list identifying all major items of tagged equipment, e.g. vessels, pumps, motors, generators, hydrocycolnes, chemical injection packages, electrical switchgear, control panels, etc.Mechanical 
17Emergency Escape & Rescue Assessment (EERA)To identify requirements for emergency escape & rescue, e.g. lifeboats, escape routes, plant layout, etc.Technical Safety 
18PFP / AFP PhilosophyDevelop philosophy that identifies requirements for Passive Fire Protection (PFP) and/or Active Fire Protection (AFP).Technical Safety 
19Power System AnalysisCheck power system capacities for increase power requirements for new equipment (Brownfield).Electrical 
20Preliminary Weight ReportPrepare preliminary Weight report.Structural 

Phase 4: Initial Design Review and Audit

To confirm that the initial design development is robust.

 Activities / DeliverablesDescriptionKey DisciplineSupporting Documentation
1Hazardous Area ReviewFormal Engineering discipline review of hazardous area layouts to confirm requirements for the correct selection and location of equipment.Technical SafetyHazard and Risk Management Procedure (DOCUMENT CODE); Engineering & Design reviews, (DOCUMENT CODE)
2P&ID ReviewFormal Engineering discipline review of P&ID’s to confirm design basis.Process, Piping, Technical Safety, Instruments 
3Plot Plans / Layout / 3-D Model ReviewFormal Engineering review of Plot Plans / Layouts. The review shall ensure that the layout design complies with the required technical, safety, operability and maintainability standards. Makes sure the layout is cost effective, ensures the constructability of the work and agrees the layout basis on which the detailed design can proceed.Piping and Layouts, Structural, Mechanical, Electrical, Technical Safety, ProcessEngineering & Design Reviews, (DOCUMENT CODE)
4C&E ReviewFormal review of Cause & Effects diagrams to confirm design basis and alignment with Hazard Management Plan.Instruments, Process, Technical SafetyHazard and Risk Management Procedure (DOCUMENT CODE); Engineering & Design reviews, (DOCUMENT CODE); Management of Functional Safety Guideline (DOCUMENT CODE)
5Technical AuditObtain confirmation, by sampling of project documentation, that the engineering of the project is to the required standard and free from errors.Independent (Corporate Engineering)Technical Audit Procedure (DOCUMENT CODE)

Phase 5: FEED Design Approval (AFD)

To ‘Freeze’ the Process design, and develop dependent design & procurement activities.

 Activities / DeliverablesDescriptionKey DisciplineSupporting Documentation
1Final Design reviewDemonstartion that all of the design and review activities relevant to achieving design integrity have been performed.Technical SafetyFinal Design Review – (DOCUMENT CODE)
2PUWER AssessmentsConduct initial PUWER assessment typically by review of PDMS model and/or vendor / equipment supplier information received to date.Technical Safety, MechanicalEngineering & Design Reviews, (DOCUMENT CODE)
3HAZOPHazard and Operability Studies, a systematic multi-discipline study based on the applications of guidewords to identify causes of potential hazards and operability constraints in a facility.Process, Technical SafetyDependent on Project updated P&ID’s and C&E’s may be prepared from commented IDC’s from Phase 3 Formal HAZOP, (DOCUMENT CODE); Engineering & Design Reviews, (DOCUMENT CODE) – Note: additional HAZOP’s may be required, i.e. earlier or later in the project. PEM to consult with Process & Technical Safety Lead Engineers.
4BAT ReportThe Final report which analyses the major environmental issues that have been considered as part of the process to select the final option from the various alternatives considered. Thus preventing, or eliminating, or where the alternatives are not practicable, to then limit or reduce environmental impacts associated with the selected option.Technical SafetyProcedure for Selection of Best Available Techniques (BAT) Procedure No: (DOCUMENT CODE)
5Constructability ReviewConduct formal Constructability Reviews to ensure safe and efficient installation of plant & equipment.Affected  disciplines + Construction / Implementation GroupEngineering & Design Reviews, (DOCUMENT CODE)
6P&ID AFDIssue Approved For Design (AFD) Process and Instrumentation Diagrams.Process 
7C&E AFDIssue Approved For Design (AFD) Cause & Effects.Instruments 
8Process Data Sheets AFDIssue Approved For Design (AFD) Process Data Sheets.Process 
9HP / LP Interface ListingIdentify all HP / LP interfaces on formal register and ensure that all have been addressed satisfactorily via HAZOP’s and / or individual reviews.Process 
10Holds RegisterDevelop register to record & manage post AFD design holds.Engineering Manager 
11SIL AssessmentsConduct assessment to determine target Safety Integrity Level (SIL). Note: Where the target SIL is 3, then it is likely that a High Integrity Pressure Protection System (HIPPS) will be required. If the value is found to be 1 or 2, then a HIPPS will not be required.InstrumentsManagement of Functional Safety, (DOCUMENT CODE)
12HIPPS StudyConduct study to formally identify the performance requirements of the High Integrity Pressure Protection System (HIPPS) and demonstrate that it is robust. Should include dynamic study for a range of transient conditions.ProcessManagement of Functional Safety, (DOCUMENT CODE)
13Qualitative Risk Assessment (QRA)Multi-disciplinary study of hazards, the likeihood of their occurrence and potential consequences in terms of harm to people and the environment.Technical SafetyFire Hazards Assessment, Blast Assessment, Dispersion Assessment, Emergency, Escape and Rescue Assessment, Heat Stess Assessment
14HIPPS Reliability StudyConduct study to formally demonstrate that the High Integrity Pressure Protection System (HIPPS) complies with the reliability & availability criteria for the Project, e.g. as stipulated in the performance standards.InstrumentsManagement of Functional Safety, (DOCUMENT CODE)
15Flow AssuranceConduct flow assurance studies to demonstrate the process design under a range of flow conditions, i.e. start-up to 100%.Process 
16EDAS Stage Gate ReviewsDemonstrate adherence to the EDAS Task Performance Crite-ria appropriate for Project Category.Engineering Management 
17Technical Peer ReviewDemonstrate adherence to the EDAS Task Performance Criteria appropriate for the Project Category and to ensure that engineering personnel are aware of EDAS requirements and adequately explain how those requirements are being fulfilled.Engineering Management 

Phase 6: Final Reviews and FEED Report Compilation

To ensure all final design deliverables are completed and that client and statutory obligations are satisfactorily resolved.

 Activities / DeliverablesDescriptionKey DisciplineSupporting Documentation
1FEED ReportCollate all discipline inputs and finalise study report.Project ManagementAll Discipline Reports and discipline drawings etc.

发表回复

您的邮箱地址不会被公开。 必填项已用 * 标注